The latest project in our garden is the 4 level terrace
It will become the Rose Garden.
The beginning of the project
Shoot the levels and organise an excavator and bobcat to shape the terraces
We estimate that this job will take about three and half days to set up 4 terraces, dig trenches where the retaining walls will go and tidy up and spread left over soil.
Update - Now that the job has progressed we know that it will take 4 days for the excavator and bobcat to complete the shaping of the 4 levels and digging the trenches plus half a day for a smaller machine to dig the trenches that the large one cannot get to.
Update - Now that the job has progressed we know that it will take 4 days for the excavator and bobcat to complete the shaping of the 4 levels and digging the trenches plus half a day for a smaller machine to dig the trenches that the large one cannot get to.
End of Day 1 - Excavation level 4 (7 am - 4 pm)
The machines (excavator and bobcat) have been in for day 1 and leveled off for the 4th terrace at the bottom of what will be the rose garden
Mid-day Day 2 - Excavation level 3 (7 am -5 pm)
End of Day 2 - Excavation level 3
The levels were all covered in black plastic so as not to wash out when it rained
16th April 2014
The blocks being unloaded for the retaining walls of the Rose Terrace.
They will be delivered in 2 loads so next week we will receive the final delivery, today we have received 6 pallets which is 1/3 of the order
Enough to get started with!
Straight blocks, left corner blocks, right corner blocks and capping blocks
Day 3 - Excavation
The machines are back today and will tidy up the top 2 levels of the terrace to enable the retaining wall to begin.
Trenches for the retaining walls
Work being done to construct the retaining walls top two levels
The machines will return in 2 weeks time to finish shaping the bottom 2 levels and digging the trenches for them
Packing down the crusher dust in the trenches
String line is set up before placing the first blocks on the crusher dust to be sure it is level
Blocks are put in place on the crusher dust
The first layer of blocks being cemented into place using the string line to be sure the blocks are level
Place the joiners |
Fill the blocks with gravel |
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.